All contractor scope tasks. Click Edit to update any task inline, or Add Task to create a new one. Drag the ⠿ handle to move a task to a different phase.
21
Total Tasks
1
Complete
1
In Progress
2
Need Clarification
5%
Phase A — Pool & Backyard Core1/9 complete
Pool draining
Complete→ ShannonApril 2
Safety railing — left side & 2 terrace areas on hill
Pending→ Shannon4/2-4/18
Rear fence addition, West side fence up entire side, repair right side planks loose
Run Cedar dog Eared planks up the left property line from steps to top of the hill. New Fence along back property line Repair the right side broken plank support
Pending→ ShannonApril 6 – April 10
Interior house painting
Pending→ ShannonApril 6 – April 10
Garage interior painting — Black Space SATIN (Marquee, walls + ceiling same color)
Pending→ ShannonApril 6 – April 10
Garage ceiling & Garage Door Drywall to Hide door from inside
The garage ceiling has an exposed area that needs to be sealed shut with drywall. The garage door needs to be sealed to look like a regular wall, making the room feel more high-end by removing the tracks and hiding the door
Pending→ Shannon4/2-4/10
Pool Water Line Tile and Coping
Please prepare an estimate based on Labor cost, we will determine the material cost once the tile selection has been made
Pending→ Primo4/2-4/18
Ring Camera at Garage Door
Need to purchase Camera
Pending→ Primo4/7 - 4/10
Gazebo Remodel
Demo decking, Remove Fire pit, Remove seating, Replace new decking and skirting
Pending→ Primo4/10 - 4 - 4/18
Phase B — Exterior & Structure0/5 complete
Pool heater installation (gas) — estimate first, proceed only if approved
Awaiting estimate approval from Karl
Needs Clarification
Address Sign (LED) Light-up Installation
Amazon link in google sheet
Pending
Wood strip column with waterproof LED strip light
Pending
Roof pressure washing and window cleaning
Pending
Turf Installation - Pool Deck (sand → turf)
Also listed in Owner scope — clarify responsibility
Needs Clarification
Phase C — Interior & Finishes0/3 complete
Perimeter fence painting or stain (left side to match right)
Pending
Driveway and pathway refinishing
In Progress→ ShannonApril 6 – April 10
Hidden door / speakeasy for garage
Pending
Phase D — Garage & Structural0/4 complete
Fireplace gas conversion to auto smart
Pending
Pool Slide - Installation
Sourcing from China
Pending
Pool Electric Awning Installation
Sourcing from China
Pending4/30
Wall Mural Painting
Pending4/20-4/30